From Conception to Construction

In 2016 KMSB recognised a requirement to support enhanced trade through the Port of Broome and proceeded to conduct feasibility studies into the construction of the new KMSB Facility.

This is the story so far, and the future for KMSB.

2016

Background due diligence performed

2017

Binding option to lease agreement with Kimberley Port Authority

2018

Preferred design solution confirmed and subsequently release of project proposal 

2019

Business case to WA State Government submitted

2020

Heritage and environmental approvals granted

Construction tender let

Operator appointment process commenced

2021

Preferred contractor appointed to design and construct Facility

2022

Detailed numerical and physical modelling confirming infrastructure’s ability to withstand severe weather events


Beyond

2023

Construction and delivery of:

+ Project fully funded

+ Commencement of construction phase

+ Finalisation and approval of detailed designs

+ Commencement of procurement phase

2024

Continued expected construction and delivery of:

+ Floating wharf

+ Abutment

+ Causeway

+ Mooring piles

+ Landside works

+ Road modules

+ Linkspan bridge

+ Restraint structures


2025

Commencement of Operations:

+ Restraint structure connections

+ Linkspan to floating wharf connections

+ Testing and commissioning